Surveying

Q1: Deviation of the actual road gradient from the proposed contou'r gradient up hill side, involves

A embankment on the centre line

B excavation on the centre line

C earth work on the centre line

D none of these.

ANS:B - excavation on the centre line

Because in hilly areas, flatter gradients are generally required which requires earthwork calculation for excavation.